Office fit-out

What should be in writing in an office fit-out quote

What an office fit-out quote in Cyprus has to state before it can be compared: scope, services, payment stages, variations and the usual exclusions.

8 min read

Office Fit Out Quotes: What Should Be in Writing — illustrasjonsbilde
ByMarina Kyriakou· Editor, commercial projects

Marina covers hotel, office, retail and restaurant refurbishment, where the binding constraint is rarely build time. In Cyprus it is occupancy: rooms are full from April to October, so the programme decides the cost more than the rate does.

Published

An office fit-out quote is comparable when it names the drawings it was priced from, states the measured area and the rate basis, prices preliminaries as a visible line, and sets out what happens when the scope changes. Anything short of that is an estimate wearing a quote's formatting, and the gap between the two is usually settled after the contractor is already on site.

Why written scope matters

The published rate for Category B office fit-out in Cyprus runs from around EUR 350 to EUR 950 per square metre once services are included — close to a threefold spread on the same unit of measurement, before anyone has described a single partition.

Category B office fit-out rates, Cyprus
WorkIndicative rangeMidpointPublished sources
Office fit-outAll-in office fit-out cost per m², covering construction works, mechanical and electrical services, furniture, technology and professional fees. No Cyprus city appears in any published fit-out cost guide, so the median is Athens — the nearest comparable market — at €1,150/m² in the Cushman & Wakefield EMEA guide. The wider Southern European cluster sits in a narrow band around it: Madrid €1,124, Lisbon €1,150, Barcelona €1,186, Rome and Milan €1,250. The low anchor is Zagreb at €750, the cheapest European city in the same guide; the high anchor is the 2025 EMEA average of €1,509/m². For scale, the guide's full European span runs from Zagreb €750 to London €2,668. Not a Cyprus observation.€750€1,500per m²€1,150
  1. Cushman & Wakefield — EMEA Office Fit Out Cost Guide 2026, average all-in costs by city (Athens €1,150/m², Lisbon €1,150, Madrid €1,124, Barcelona €1,186, Rome €1,250, Milan €1,250)read 2026-08-02
  2. Cushman & Wakefield — office fit-out costs in Europe stabilise (2025 EMEA average €1,509/m², up 3.8 % year-on-year across 53 cities; European range €750 Zagreb to €2,668 London)read 2026-08-02

Indicative range compiled from published sources, not a quote. It shows the level those sources report for this kind of work, not what your job costs. Only a site visit and a written quote for your actual scope produce a real figure. Sources compiled 2026-08-02.

General commercial interior work, shell to occupied, sits on a wider band again at roughly EUR 420 to EUR 1,150 per square metre. A quote landing anywhere inside those ranges tells the reader almost nothing on its own. What tells them something is the scope behind the rate.

Three phrases do most of the damage. Open-plan refurbishment can mean re-decorating an existing layout, or stripping cellular offices, re-balancing the cooling and re-running every data drop. New air conditioning can mean replacing splits on existing pipework, or a ducted system needing a ceiling void the building may not have. Bring the electrics up to standard can mean new final circuits, a new distribution board, or a supply upgrade involving the utility and a lead time no amount of site labour compresses.

Building stock makes this worse. Much of the office floorspace in Nicosia sits in concrete-frame blocks built between the 1970s and the 1990s, where the constraint is rarely the finishes but slab-to-slab height, the absence of a usable ceiling void, and services designed for a different occupancy. Strovolos is dominated by that generation of building, and rewiring and replumbing routinely turn out to be the larger half of a job described as cosmetic. Central Limassol reverses the pattern: recent high-rise stock has good service provision but shared lifts, booked delivery slots, and facade and balcony conditions of its own.

Nicosia's climate is a specification input, not background detail. The inland location produces the widest temperature range on the island, which is why cooling capacity, glazing performance and shading on west-facing elevations belong in the scope rather than in the contractor's judgement. The sector pages and district coverage on this site separate the fit-out types for the same reason.

The eleven items a quote needs

  1. 1. The drawing register, with revision numbers

    A quote priced from "the layout we discussed" has no defence when the layout changes. Naming each drawing and revision fixes the baseline, and decides whether a later change is genuinely a variation.

  2. 2. Measured area and the basis of the rate

    Net internal, gross internal and the area actually worked on are three different numbers in the same building. Say which one the rate applies to, and whether it is per square metre, per workstation or a lump sum.

  3. 3. Preliminaries, priced as their own line

    Site set-up, protection, supervision, welfare, insurance, access equipment and waste. Buried in a rate they are invisible; on their own line they show which contractor has understood the access constraints.

  4. 4. Strip-out, disposal and what is retained

    What comes out, who removes it, and what is protected and handed back undamaged. Carpet, ceiling tiles and light fittings are often assumed reused by one contractor and removed by another.

  5. 5. Partitions, doors and internal glazing

    Construction, acoustic rating, whether partitions run to the underside of the slab or stop at the ceiling, and glazing specification. Acoustic performance between meeting rooms is the item most often quietly downgraded.

  6. 6. Ceilings, floor finishes and decoration

    Demountable grid or jointed plasterboard, access provision, floor build-up and levelling, and how many coats over what preparation. Levelling an old screed is a cost no floor plan reveals.

  7. 7. Mechanical services, including fresh air

    Cooling capacity and how it was calculated, indoor unit type and position, condenser location and route, condensate drainage, and whether ventilation is included. Condenser positions on a shared elevation need consent, and consent has a lead time.

  8. 8. Electrical, data and containment

    Circuit provision, board capacity, containment routes, floor boxes, outlet counts, and who terminates and tests. Cabling supplied by one party and terminated by another is a standing dispute.

  9. 9. Fire and life safety

    Detection and alarm alterations where the layout changes, emergency lighting, signage, and fire-stopping where partitions or services cross a fire line. This is the line most often absent from the lowest quote and the hardest to add once ceilings are closed.

  10. 10. Builder's work in connection, and make-good

    Chasing, coring, fire-stopping and making good around mechanical and electrical installations. When neither the main contractor nor the services subcontractor has priced it, it surfaces first as a gap in the programme and then as a cost.

  11. 11. Programme, working hours and handover

    Duration in weeks, a handover date, permitted working hours and the defects period. Work confined to evenings and weekends buys the same labour at a premium; if the quote does not say which hours it assumed, it assumed the cheap ones.

Two further points belong on the same page. The quote should state whether figures include VAT and which treatment the works fall under, because quotes on different bases will not reconcile. It should also say who handles statutory approvals where the works change layout, use or envelope — that route runs through the Department of Town Planning and Housing and takes time outside the contractor's control.

Payment stages

Monthly valuation against work in place is the standard commercial arrangement. The contractor applies for what has actually been built that month, it is assessed, and the assessed sum is paid. The mechanism is self-correcting: if progress slows, so does payment.

Stage payments tied to named milestones — strip-out complete, first fix complete, ceilings closed, practical completion — suit shorter programmes. Their weakness is that a milestone is a matter of judgement, so each stage needs defining in writing beside its sum.

Four questions decide whether either structure is sound. Who certifies value, and on what evidence. Whether any sum is payable before work starts and what it covers, since a mobilisation payment against ordered materials is not the same as a deposit funding cash flow. Whether a retention is held and when it is released, because one released entirely at practical completion gives no leverage over defects. And whether payment is triggered by the calendar or by an event, since a date that arrives regardless of progress removes the incentive to hold the programme.

Variations and how they are priced

Every fit-out changes after it starts. The variable is whether the pricing mechanism was agreed while the contractor was still competing for the work.

A workable variation clause requires instructions in writing before the work is carried out; fixes the rates additional work is priced at, by reference to the original quote or a short agreed schedule; requires the time consequence to be stated alongside the cost, since an extended programme is the more expensive half of most variations; and requires the revised total to be confirmed before work proceeds.

Two terms are worth separating. A provisional sum is an allowance for work that is known about but not yet priceable — an unopened ceiling void, an undocumented incoming supply — and is expected to be replaced by a real price. A prime cost sum is an allowance for an item the client has not yet chosen, where installation is priced but the item is not.

Red flags

  1. A single lump sum with no breakdown

    It cannot be compared, valued mid-programme, or adjusted when scope changes. A breakdown by trade is the minimum.

  2. No exclusions list

    Every quote has exclusions. One that does not print them has left them undiscussed. Asbestos and structural surveys, statutory approvals, temporary works, out-of-hours access and make-good are the usual five.

  3. Fire and life safety absent from a layout change

    Where partitions move, detection, emergency lighting and compartmentation move with them. Silence means it was not priced or not noticed.

  4. A price with no programme

    Commercial occupiers buy a date as much as a specification. A price without a duration and a handover date is half a quote.

  5. No site visit before pricing

    Ceiling void depth, riser positions, board capacity and the goods route cannot be read off a floor plan. A quote priced without a visit priced an assumption, corrected later at the occupier's expense.

Common questions

How many quotes are worth collecting?

Three, priced against the same drawing register and services scope. A fourth quote against a loose scope adds noise rather than information. Where three prices are far apart, the scope is usually the problem rather than the market, and tightening the documents closes more of the gap than negotiating will.

Is a rate per square metre or a lump sum better?

A rate per square metre is useful for early budgeting and for checking a proposal against the published ranges. A lump sum against a drawn scope is what should be signed. The rate answers roughly what this costs; the lump sum answers what this specific job costs.

Can an office be fitted out while staff keep working?

Frequently, at a premium larger than most occupiers expect. Phasing adds remobilisation, temporary protection, restricted hours, dust and noise separation and a segregated materials route. It is justified when the cost of decanting exceeds that premium, and the comparison is worth making with a number.

What usually causes delay on a Cypriot office fit-out?

Long-lead items and consents rather than site labour. Glazed partition systems and cooling plant are ordered against a lead time, condenser positions on shared elevations need the building owner's agreement, supply upgrades involve the utility, and supplier availability tightens around the August shutdown period.

Does the contractor or the occupier hold the approvals risk?

Whichever the contract says, which is why it needs saying. Where works alter layout, use or the envelope, an approval route applies through the Department of Town Planning and Housing and the application is normally prepared by a professional registered with ETEK. If the quote is silent, that risk has defaulted to the occupier.

Contractors documenting workplace projects

No companies listed here yet.

Sources

  1. Cyprus Scientific and Technical Chamber (ETEK) — retrieved 2026-07-29
  2. Department of Town Planning and Housing — retrieved 2026-07-29
  3. Tax Department — VAT on construction works — retrieved 2026-07-29

Thinking of doing this?Get up to five quotes, free.

Tell us about the property and we will gather quotes from contractors who plan around the season.

Get up to 5 quotes.Free, with no obligation.

Tell us briefly what you need. We gather quotes from qualified companies where you live, so you do not have to ring round yourself.

Free · No obligation · You decide whether to go ahead