Hotel refurbishment

What hotel refurbishment costs in Limassol and across Cyprus

What a hotel refurbishment costs in Limassol and across Cyprus, priced by room and by scope, with the closed-season programme built in.

8 min read

What Hotel Refurbishment Costs in Cyprus in 2026 — illustrasjonsbilde
ByMarina Kyriakou· Editor, commercial projects

Marina covers hotel, office, retail and restaurant refurbishment, where the binding constraint is rarely build time. In Cyprus it is occupancy: rooms are full from April to October, so the programme decides the cost more than the rate does.

Published

A mid-market guest room in Cyprus, stripped back to the shell and rebuilt to a finished, lettable standard, runs between €8,500 and €28,000 per key, with the median sitting at €15,000. That is the figure an owner should hold in mind before any contractor is approached, because almost every quote that arrives later will be a variation on it. What moves a Limassol hotel from the bottom of that range to the top is not the quality of the carpet. It is the depth of the strip-out, whether the property trades through the works, and how much of the corridor, lobby and back of house has been loaded into the per-key figure.

Guest room refurbishment, Cyprus
WorkIndicative rangeMidpointPublished sources
Hotel refurbishmentGuest-room refurbishment budget per key, Western European benchmark. Covers FF&E and OS&E only — furniture, fixtures, equipment and operating supplies — and explicitly excludes mechanical and electrical works, bathroom refurbishment, structure and back-of-house. Published bands are €8,000–15,000 per key for budget 2–3★, €15,000–28,000 for midscale 3–4★, €28,000–55,000 for upscale 4–5★ and €55,000–120,000+ for luxury. The median sits inside the midscale band because most Cypriot hotel stock is 3–4★ resort. No Cyprus-specific refurbishment cost is published; the Cyprus Statistical Service figure of €2,202/m² for hotels is new-build construction of whole buildings, a different scope, and is not used here. Tier-1 cities such as Paris and London carry a 20–35 % premium over regional markets. VAT treatment is not stated. Treat as the weakest-sourced row in this file: the publisher is a hospitality cost consultancy that states no underlying methodology.€8,000€55,000per room€20,000
  1. Figurz — hotel FF&E and OS&E budget per room, Western Europe benchmark (budget €8,000–15,000/key, midscale €15,000–28,000, upscale €28,000–55,000, luxury €55,000–120,000+; renovation runs 15–25 % above new build)read 2026-08-02

Indicative range compiled from published sources, not a quote. It shows the level those sources report for this kind of work, not what your job costs. Only a site visit and a written quote for your actual scope produce a real figure. Sources compiled 2026-08-02.

The short answer

The range above covers a room taken back to blockwork and screed, with new bathroom, new services within the room, new joinery, new FF&E and making good to the corridor. It does not cover the rest of the building, and this is the first place comparisons break down.

Three refurbishment depths sit inside the same headline vertical, and they are not interchangeable:

  • Soft refresh. Soft furnishings, case goods, decoration, lighting fittings. No services touched, no sanitaryware moved. Sits at or below the lower end of the range.
  • Room refurbishment. New bathroom in the existing footprint, new finishes, new electrics within the room, retained partitions and risers. This is what the median describes.
  • Full strip-out with reconfiguration. Bathroom relocated, partitions moved, riser drops altered, plant capacity revisited. This is what pushes a project to the upper end, and it is the only one of the three that reliably triggers a permit application.

A Limassol seafront property that has never been substantially altered since it was built will usually need the second or third of those, not the first, because the bathroom waste falls and the electrical distribution are the constraints rather than the decoration.

What drives the range

  1. Trading through the works

    This is the largest single multiplier and the one most often left out of an owner's own estimate. A hotel that closes for a season pays for one mobilisation, continuous trade sequencing, unrestricted working hours and no guest interface. A hotel that refurbishes floor by floor while trading pays for remobilisation, temporary protection, separated material routes, restricted hours and the comped nights that follow noise complaints. The build is the same. The programme is not.

  2. Bathroom strategy

    Keeping the bathroom in its existing footprint and reusing the waste stack is the difference between a room refurbishment and a services project. Once the stack moves, the floors above and below are in scope whether or not they were in the brief.

  3. What the building envelope forces

    Balcony waterproofing and facade repair are not guest room costs, but on Cypriot coastal stock they arrive at the same time. Facade work is priced separately, in the region of €55 to €175 per m² for render repair, coating and balcony edge detail, and it carries its own access cost.

  4. Access and scaffolding duration

    Scaffolding is charged for erection, hire and dismantling at roughly €4 to €13 per m² per week. Because it is a weekly charge, programme length rather than building height is what makes it expensive, and a phased job that keeps scaffold standing across two shoulder seasons can cost more in access than in render.

  5. Plant and energy scope

    Where HVAC, glazing and insulation are packaged into the refurbishment rather than bolted on afterwards, the work is priced closer to €120 to €380 per m² as an energy retrofit line. Bundling it with the strip-out is cheaper than returning for it, because the ceilings are already down.

Cost by district

There is one national price series for guest room refurbishment, not five. That is a deliberate limitation: room specifications vary far more between two hotels on the same Limassol street than they do between districts, and publishing a district multiplier would imply a precision the data does not support. What does change by district is the condition of the stock and the cost of getting labour and materials to it.

Limassol. Rapid high-rise development along the coast has pushed demand towards balcony waterproofing and facade maintenance, and that demand competes for the same specialist crews a hotel needs. On tower stock, material handling runs through a single service lift, which lengthens programmes and therefore the access bill. Whether local contractor availability offsets any of that is worth testing at tender rather than assuming — see the Limassol coverage page for what is active locally.

Famagusta district — Ayia Napa, Protaras, Paralimni. Almost all accommodation here is seasonal, so refurbishment is compressed into November to March. The consequence is not a higher rate card but a thinner field: the contractors with hospitality experience commit their winter capacity early, and a programme agreed in September for the same winter is bidding for whoever is left.

Paphos. Direct coastal exposure at Kato Paphos means salt-laden air, and galvanised or marine-grade fixings are standard rather than an upgrade. Balcony balustrades, external ironmongery and window hardware all specify differently. Inland and hillside sites at Peyia have steep access roads that limit crane and delivery vehicle size, which changes how a bathroom pod or a curtain wall panel reaches the building. Polis Chrysochous sits far enough from the Paphos contractor base that travel time is embedded in most quoted day rates.

Larnaca and Nicosia. Larnaca's proximity to the salt lake raises humidity around Oroklini, which shows up in damp-proofing specifications. Nicosia is business-hotel stock with the widest temperature range on the island, so glazing and shading carry more weight in the specification than sea-facing finishes do.

What is usually excluded

Read every quote against this list before comparing it to another.

  • Common areas and back of house. Lobby, stairwells, corridors and lighting are typically a separate line, in the order of €180 to €560 per m². A per-key number that excludes them is not wrong, but it will not reconcile with the total when the board asks.
  • Plant and vertical transport. Chillers, lift refurbishment and switchgear are routinely carved out and then arrive as a variation.
  • Design fees and statutory approvals. Where layout or the envelope changes, planning and building permit applications go through the Department of Town Planning and Housing and the relevant municipality, and the design team needs to be appointed early enough for that to run in parallel with procurement rather than after it.
  • Asbestos and unforeseen ground or structure. Older stock frequently produces both. A quote with no provisional sum against opening up is a quote that will grow.
  • FF&E lead times. Not a cost line, but the reason winter programmes slip. Long-lead sanitaryware and joinery ordered after the strip-out has started is the classic Cypriot shoulder-season overrun.
  • VAT. Confirm whether the rate applied is the reduced or standard rate for the works in question, and whether the figure quoted is inclusive.

How to compare quotes

Ask every tenderer to price the same three things separately: the guest room, the allocated share of common areas and back of house, and the phasing premium. Once those are split, quotes that looked far apart usually turn out to differ on scope rather than rate.

Then check the following before signing.

  1. Is the per-key figure on the same basis? Rooms only, or rooms plus allocated common parts. State which one the tender is on and require all bidders to follow it.
  2. What programme is priced? Full closure, floor by floor, or room by room while trading. A rate without a programme is not a price.
  3. Who supervises? For work of this scale, a qualified architect or civil engineer registered with ETEK should be named, and the appointment should be the owner's rather than the contractor's.
  4. How are variations priced? Agreed rates for common variation types, in writing, before work starts. Day-rate variations negotiated mid-programme are where budgets fail.
  5. What is the retention and the defects period? Coastal properties should want a defects period that spans at least one full summer, so that waterproofing and cooling performance are tested under load.
  6. Is there a provisional sum for opening up? On any building whose services and waterproofing have never been renewed, there should be.

Owners comparing a phased refurbishment against a full closure will find the sector pages and the wider comparison of refurbishment approaches on this site more useful than a single rate, because the decision is a programme decision before it is a cost one.

Contractors documenting hospitality projects

No companies listed here yet.

Common questions

How much does a hotel bathroom refurbishment cost in Limassol?

It is not usually priced on its own. Bathrooms are the largest single component of the per-key figure, and a room where the bathroom stays in its existing footprint sits materially lower in the €8,500 to €28,000 range than one where the waste stack moves. Ask for the bathroom to be shown as a separate line within the room build-up, so the effect of retaining the footprint is visible.

Is it cheaper to refurbish in winter?

The work is cheaper to do in winter because rooms are empty, but it is not cheaper to buy late. Seasonal properties across the Famagusta district and coastal Paphos all target the same November to March window, so contractor availability tightens as the season approaches. Committing early buys both the programme slot and the rate.

Does a guest room refurbishment need a permit?

Redecoration and like-for-like replacement generally do not. Moving partitions, altering the facade, changing the layout or altering means of escape generally do. The distinction is made by the Department of Town Planning and Housing and the municipality, and it should be settled at design stage rather than assumed.

What is a realistic contingency?

Enough to cover opening up on stock of unknown condition, held by the owner rather than absorbed into the contract sum. On buildings where the services have never been replaced, a contingency that only covers finishes is optimistic.

How long does a floor take?

That depends on the number of keys on the floor, whether the riser is accessible from the corridor, and how many trades can work concurrently under the noise restrictions the hotel imposes while trading. Ask each contractor for a programme per floor rather than a total, because the floor rate is what reveals whether the overall date is achievable.

Sources

  1. Cyprus Statistical Service — construction cost and price indices — retrieved 2026-07-29
  2. Department of Town Planning and Housing — planning and building permits — retrieved 2026-07-29
  3. Cyprus Scientific and Technical Chamber (ETEK) — retrieved 2026-07-29

Thinking of doing this?Get up to five quotes, free.

Tell us about the property and we will gather quotes from contractors who plan around the season.

Get up to 5 quotes.Free, with no obligation.

Tell us briefly what you need. We gather quotes from qualified companies where you live, so you do not have to ring round yourself.

Free · No obligation · You decide whether to go ahead